Hazelhead Wind Farm

Construction of 3 no reinforced concrete wind turbine bases, The metmast and substation bases. The project comprises of approximately 110 tonne of reinforcement , 700 cubic meters of concrete and 275 m2 of radius and rectangular formwork. The programmed period for the reinforced concrete works was 6 weeks, JS Structures completed the reinforced concrete works in 5 weeks.