The project started with the construction of the reinforced concrete AHU Slab & Then the construction of the reinforced concrete Sprinkler & Pump House Slabs And Plinths. Followed by the concrete encasement column surrounds 84no. The Click and collect reinforced concreteretaining wall and then the reinforced concrete 3500 sq mtr ground floor slabs, constructed in 3 pours. Finally the construction of the goods online buliding floor slab. JS Structures completed the reinforced concrete works late July 2011. | |