JS Structures were asked on Wednesday 6th April if we could get a temporary works design done for the reinforced concrete walls to the 2 no machine pits to the reinforced concrete ground floor slab and formwork to site on Friday 8th April against all the odds JS Structures achieved this. Snowden flooring asked us if we could work the whole weekend of the 9th & 10th April to fix the steel reinforcement and formwork to the 2no Reinforced concrete pit walls and concrete them on Monday 11th April and strike the wall formwork on Tuesday 12th April to enable them to continue with the reinforced concrete ground floor slab on programme. The Size of the Reinforced Concrete Pit walls were 7.5mtrs long x 3mtrs wide by 2.5mtrs high.
JS Structures are proud to announce all was achieved. |