Markham Vale

The project Commenced on 16-05-12 and was completed 26-06-12. The project comprised of 5500m2 of reinforced brush finished concrete to the service yard slab for the new Andrew Page Building at Markhamvale. The reinforced concrete slab was constructed in 10 pours and took 6 weeks with a 2 week delay after the 2nd week which means it was constructed in 4 weeks.